Ten things to go through at the first meeting
Allow 60 to 90 minutes, depending on the size of the house.
- 1How the supply comes in: underground or overhead.
- 2Where the service pit or pole sits, and its distance from the house.
- 3Where you'd like the electricity meter.
- 4Single occupancy or multiple (units).
- 5Power outlets: type, colour, how many and roughly where in each room. Include weatherproof ones outside and any in the ceiling for ducted heating and cooling.
- 6Lighting: the type of fittings, how many and where, inside and out.
- 7Appliances: oven, hotplates, hot water, air conditioning, ceiling fans, heating, garage door openers, spa, bathroom heat and fan units, exhaust fans, workshop gear. We need the load of each and whether it's single or three phase, to confirm the supply's big enough.
- 8TV points, phone points and home networking.
- 9Smoke alarms: how many and where.
- 10Home automation, if you want it.
From that we can put together a quote that covers everything you went through. Get two or three quotes, and don't choose on price alone. Think about who actually helped you understand the design, and who you'll find easy to talk to when the plans change. They always change.
How the job runs
- 1Before the slab is poured: the underground service and builder's post go in, with the phone conduits in the same trench.
- 2Once the slab's down: the builder's temporary supply goes in, usually where the permanent one will be. We organise the inspection and paperwork to get it connected. You pick your electricity retailer and open the account.
- 3Rough-in: once the frame, windows, brickwork and roof are up, we run all the cable through the frame. Outlet and switch positions come off the final plan or a walk through the house with you.
- 4Once the plaster's on: we cut out every outlet, switch and downlight position, so the tilers can get on with it and everything's found before the painters arrive.
- 5Fit-off: with the kitchen and bathrooms fitted and the painting done, the power points, switches, light fittings, smoke alarms and appliances go in, and the switchboard is fitted out with safety switches and circuit breakers.
- 6Test and energise.
There's more to it than that, but it's a good start. Start early and think through what you need at the beginning.